Construction begins on 80MW solar power plant at Northam Zondereinde

Construction begins on 80MW solar power plant at Northam Zondereinde

Northam

Northam Platinum Holdings Limited (Northam) has finalised a Power Purchase Agreement (PPA) with an Independent Power Producer (IPP) in respect […]

Northam Platinum Holdings Limited (Northam) has finalised a Power Purchase Agreement (PPA) with an Independent Power Producer (IPP) in respect of an 80MW solar power plant to service its Zondereinde operation near the town of Thabazimbi in the Limpopo province. Construction has commenced with power expected to be available from December 2025.

This plant will deliver 220GWh of energy per year directly into Zondereinde’s mining and smelting operations, independent of the Eskom grid, reducing the operation’s carbon footprint by 22%. Further benefits include significant cost savings and reduced power supply risk.

The IPP comprises a consortium including the STANLIB Infrastructure Fund II, Royal Bafokeng Holdings Proprietary Limited and Energy Group. Project finance is being provided by Nedbank Limited (acting through its Nedbank Corporate and Investment Banking Division) and the Standard Bank of South Africa Limited (acting through its Corporate and Investment Banking Division).

Paul Dunne, Northam’s CEO, welcomed the PPA, stating that, “Northam is committed to sustainably reducing the environmental impact of our operations, and this, our first major renewable energy project, represents a significant milestone. The environmental, operating cost and energy security benefits implicit in this initiative add additional resilience to our world-class Zondereinde mine.”

The project is part of a broader strategy to reduce Northam’s environmental impact whilst securing the supply of bulk services. This includes a reduction in carbon intensity by 60% from a 2019 baseline by 2030, whilst improving power availability and decreasing overall electricity costs.

Northam says that it is at an advanced stage of progressing additional renewable energy projects in a dynamic and rapidly changing technological and legislative environment. This includes solar, wind and battery storage initiatives.

Source: supplied by Northam Platinum Holdings Limited

Share:

More Posts

Rokbak revels in stable ADT demand

At Nigeria Mining Week, Rokbak and its West Africa dealer HMD presented the RA40, which attracted substantial interest. The Scottish-made haulers are fast proving to be popular in the African mining, quarrying and infrastructure sectors thanks to the trucks’ reliability and durability.

Compact footprint, full performance: Link-Belt unveils 245 X4S excavator

The 245 X4S, which debuted at ConExpo, enters the market as a technology-ready solution, offering optional advanced features such as digital level, height and depth alarms, and an integrated payload system.

Send Us A Message

Scroll to Top